http://rdf.ncbi.nlm.nih.gov/pubchem/patent/JP-2019168158-A
Outgoing Links
Predicate | Object |
---|---|
assignee | http://rdf.ncbi.nlm.nih.gov/pubchem/patentassignee/MD5_32eb4e70670495ea43d82928b3e95899 |
classificationIPCInventive | http://rdf.ncbi.nlm.nih.gov/pubchem/patentipc/F27D1-16 http://rdf.ncbi.nlm.nih.gov/pubchem/patentipc/C04B35-66 |
filingDate | 2018-03-23-04:00^^<http://www.w3.org/2001/XMLSchema#date> |
inventor | http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_ddd793fd2cb841f43bab7dc12adff4b7 http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_0ce9ee94fb2739897c332f031505f74f http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_087c0b78f729eb233ddc9521d0970d14 http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_f9a613d441793b43c957cf6f5450069c http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_b7447cc489e2561a98e1cc33581e2f4d http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_2891f31d54cd853c4e4b5da60161a277 |
publicationDate | 2019-10-03-04:00^^<http://www.w3.org/2001/XMLSchema#date> |
publicationNumber | JP-2019168158-A |
titleOfInvention | Method for spraying irregular refractories and spraying materials used therefor |
abstract | [PROBLEMS] To provide a water injection device in a material transport pipe from a material supply machine to a tip spray nozzle, and to spray an unstructured refractory that injects construction water into the spray material transported through the material transport pipe from the water supply device. In the method, the stability of the spraying construction is improved. A water injection device is provided in a material conveyance pipe from a material supply machine to a tip spray nozzle, and the construction water is injected into the spray material conveyed in the material conveyance pipe from the water injection device. in spray construction method of a product, the ratio of the flow rate of the construction water carrier gas for transporting the construction water introduced into the water injector 7 (Nm 3 / min) and construction water (m 3 / min) (construction water The flow rate of the conveying gas / the amount of construction water) is 100 to 1000. [Selection] Figure 1 |
priorityDate | 2018-03-23-04:00^^<http://www.w3.org/2001/XMLSchema#date> |
type | http://data.epo.org/linked-data/def/patent/Publication |
Incoming Links
Total number of triples: 40.