http://rdf.ncbi.nlm.nih.gov/pubchem/patent/CN-109437357-A

Outgoing Links

Predicate Object
assignee http://rdf.ncbi.nlm.nih.gov/pubchem/patentassignee/MD5_e1a33cacff26b79bf76df0921938846e
classificationCPCAdditional http://rdf.ncbi.nlm.nih.gov/pubchem/patentcpc/B01D2009-0086
http://rdf.ncbi.nlm.nih.gov/pubchem/patentcpc/C02F2103-06
classificationCPCInventive http://rdf.ncbi.nlm.nih.gov/pubchem/patentcpc/C02F1-20
http://rdf.ncbi.nlm.nih.gov/pubchem/patentcpc/B01D9-0063
classificationIPCAdditional http://rdf.ncbi.nlm.nih.gov/pubchem/patentipc/C02F103-06
classificationIPCInventive http://rdf.ncbi.nlm.nih.gov/pubchem/patentipc/C02F1-20
http://rdf.ncbi.nlm.nih.gov/pubchem/patentipc/B01D9-02
filingDate 2018-11-28-04:00^^<http://www.w3.org/2001/XMLSchema#date>
inventor http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_16f372b4c5ad6c26126dbc224ab1604e
http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_787baf41d9916a962c4f6c28bb0c5e37
http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_873704f74a0c52b114f2d9e75ea6bbe0
http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_edc8708d1ef8f680825adb55575c616d
http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_742604183d2ad4f726efe4469a0630c1
http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_83a3162dc80f16caf05bd73b2ae502f4
http://rdf.ncbi.nlm.nih.gov/pubchem/patentinventor/MD5_52f78109d6225743c793bbecfd746e6d
publicationDate 2019-03-08-04:00^^<http://www.w3.org/2001/XMLSchema#date>
publicationNumber CN-109437357-A
titleOfInvention Installation method of ammonia stripping and crystallization system in narrow space of enclosure structure
abstract The invention relates to the technical field of ammonia stripping and crystallization systems, and discloses an installation method for an ammonia stripping and crystallization system in a narrow space of an enclosure structure, comprising the following steps: (1), checking and accepting equipment and concrete foundations; (2) , hoist and install a plurality of the stripping towers, the stripping towers include the top head, the first tower section, the second tower section, the third tower section and the bottom of the tower connected in sequence from top to bottom (3), hoist and install the crystal tower; (4), apply BIM technology, design the installation and construction sequence of the process pipeline; (5), complete the process according to the pre-designed installation and construction sequence of the process pipeline Pipeline installation; this construction method solves the limitation of indoor hoisting capacity, and adopts segmented and layered hoisting and installation; BIM construction technology is applied in the installation of process pipelines, the construction sequence is reasonably arranged, the problem of cross collision is solved in advance, and good economic benefits and social benefit.
priorityDate 2018-11-28-04:00^^<http://www.w3.org/2001/XMLSchema#date>
type http://data.epo.org/linked-data/def/patent/Publication

Incoming Links

Predicate Subject
isDiscussedBy http://rdf.ncbi.nlm.nih.gov/pubchem/substance/SID447858798
http://rdf.ncbi.nlm.nih.gov/pubchem/compound/CID222
http://rdf.ncbi.nlm.nih.gov/pubchem/compound/CID6857397
http://rdf.ncbi.nlm.nih.gov/pubchem/compound/CID24655
http://rdf.ncbi.nlm.nih.gov/pubchem/substance/SID448315045
http://rdf.ncbi.nlm.nih.gov/pubchem/substance/SID419512635
http://rdf.ncbi.nlm.nih.gov/pubchem/compound/CID962
http://rdf.ncbi.nlm.nih.gov/pubchem/substance/SID419550829

Total number of triples: 30.